Hi Virginia,
"Working resources breakdown" = Report will only show resources who have work assigned to them on that specific Project, and Timeframe. If no Work has been assigned to a resources for the time period, one will see only resources who reported time at any given point during the Project.
"All resources breakdown" = Report will show all resources, including Work Item Managers with no direct work assigned to them.
Makes Sense?