Stacy,
Is the Task still Active (not Completed)? If this is the case, it will continue to show until completed. If this is not the issue, please provide a screen capture showing the Timesheet view and highlight the Task that should not be there. Then provide a secondary image showing the Task properties (specifically Resources, STart/Due date, %complete, actual effort and remaining effort).
Sincerely,
Boris