Can I default milestones to "Show with Date" in roadmap?

Rather than change this setting in each project plan, is it possible to default milestones in the project roadmap to "Show with Date?" The clients want to see the dates. Thank you.

Abby Mcgrady Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Hi Abby,

What you can do is make sure your the milestones in your project templates are set with "Show with date" enabled so that all new projects going forward will have the dates showing in the roadmap.

If you need assistance, please log a support case and we'll be happy to provide detailed information or jump on a quick screenshare with you.

 