Is there a maximum number of resources on a given project?

Hi Everyone:

We are  new Clarizen customer and are trying to decide whether to have one Administrative (non-billable) project or multiple for different managers.  Both could work, but we are wondering if there is a maximum number of resources we can assign to a project?  We may have 80-100 resources on one administrative project with multiple direct managers approving time for their reports.  Any gotchas with doing this?

 

Thanks

 

Lori

lmathis Answered

Please sign in to leave a comment.

2 comments

0
Avatar

Lori,

There is No limit. Performance can be affected. It depends on the usage, for example opening resources load screen with many resources affects page load time.

Sincerely, 

Boris Krutiy - Clarizen Success

Boris Krutiy 0 votes
Comment actions Permalink
0
Avatar

Is this still true today, August 2021?  We are seeing managers (additional managers) falling off projects that they were once managers on previously.  Why is this occurring?

Coates, Kimberly 0 votes