Budgeted Cost

Budgeted Cost

Authorized users can see a work item’s Budgeted Cost in the Budget or Extended Budget views of either the Work Items page or the Current Project page and in the Properties of the work item. 

The system automatically calculates Budgeted Cost of the work item as a sum of its sub-items:

  • Accumulative Budgeted Cost of the sub-items or the Fixed Cost, if defined for the work item.
  • Planned Expenses

 Budgeted Cost of the “leaf” work item is calculated as a sum of:

  • Work (estimated effort) planned for specific resource multiplied by the Cost Rate of the resource or the Fixed Cost, if defined for the work item.
  • Planned Expenses

 User can:

  • See the amount allocated to the selected work item. 
  • Manually enter the cost of the work item. In this case, the cell is marked by a blue triangle. This value overrides the accumulative value of the sub-work items and it will be used to calculate the budget of work items higher in its hierarchy.
  • Clear the Manually set indicator (blue triangle), thereby telling the system to recalculate the budget values automatically.
Clarizen Team Answered

Please sign in to leave a comment.

2 comments

0
Avatar

I appreciate the information provided. It was really helpful to configure Clarizen.

 

Erik Valdovinos 0 votes
Comment actions Permalink
1
Avatar

Hi,

I accidentally overrode the budgeted cost in my portfolio properties and now the blue traingle indicator on my portfolio will not go away. Clarizen still thinks that I have a manual input in the field even though I deleted the value in there. It is impacting my ability to to run financial planning. Please help.

Thanks,

The Clarizen Questioner

Clarizen Questioner 1 vote
Comment actions Permalink