Explanation Point on Project Icon

 I just uploaded holidays for 2016 and 2017 and see explaination points on some project icons. What does this mean? 




Pam Dye Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Pam, 

This means that the system has scheduled to 'recalculate' the Project and its child work items to update all fields (dates, durations, etc.). If you want to speed up the process, you can click on the drop down menu to the right of the exclamation and select recalculate or click on the Project and select the same from the Property Card menu.