Here's my use case...
I have a series of 10 tasks in a milestone.
So, it's as though CZN is treating this resource as a different person. I suppose I could set each task as a predecessor to the next, but since it's the same guy with the same max allocation, I'd figure CZN would just push each task downstream after the next was completed.
Is there an easier way to do this?
Please sign in to leave a comment.
bump
Hello,
To address your issue, it is important to understand the default behavior of the WBS and how the Hierarchy of the Projects, Milestones and Tasks works. By default, 10 Tasks within a Milestone will ALWAYS have the same start date based on the Milestone date unless manually changed. The system does not assume that each task will be assigned to the same Resource or cannot be done simultaneously. The Predecessor functionality allows you to specify these 10 tasks to start once the previous ends thus "pushing task downstream" based on when the Due dates are specified.
Also, the explanation to your concern about the due date being based on Duration is that you are specifying Fixed Work as your Work Policy. Unless you manually override the duration, the Clarizen system will automatically calculate the Duration based on Work and Unit% as specified at the Resource Panel.
As an example, I will use max allocation of 50% to make it easier. The resource works 8 hours a day so the allocation is 4h per day. A task with 8h of work will auto-calculate the Duration to 2 days.
Hopefully, this explains this scenario for you. For further information, here are some links to our documentation...
https://success.clarizen.com/hc/en-us/articles/205711858-17-2-Work-Policy?search=work+policy
https://success.clarizen.com/hc/en-us/articles/205712528-4-1-Work-Items-Overview?search=predecessor
https://success.clarizen.com/hc/en-us/articles/206449367-4-5-Resource-Management