custom action to copy a task from one project to another project

Is it possible to build a custom action to copy a task from one project to another project?

Set Action in the CA has "move item" but I couldn't see copy/paste. is it covered in another action?

Avnish Bhardwaz Answered

Please sign in to leave a comment.

3 comments

0
Avatar

Hi Avnish,

 

If that task don't have sub tasks, just create new item > task and copy the values manually from the CurrentObject() and change the parent to the new project.

 

Let me know if that makes sense.

 

Good luck!

Tamir

Tamir Avital 0 votes
Comment actions Permalink
0
Avatar

Thanks, Tamir

 

This is very help and works.

 

I want to add a second item to update discussion topic on the current task to indicate that task has been copied. I selected Set Action 2 as Pin/Highlight Select Object Topic.

 

What goes in Container and Discussion Box? it doesn't take text it is expecting $filedname.  I just want a text that this task has been copied on the discussion topic of current task.

Avnish Bhardwaz 0 votes
Comment actions Permalink
0
Avatar

Avnish,

 

Can you please attach a screenshot of what you expect to happen in the UI?

 

Thanks,

Tamir

Tamir Avital 0 votes