Reporting and Viewing Lag

We utilize lag in many of our projects and project templates.  I am looking to either have a view which will show the lag time without clicking into the link icon under Number of Predecessors column, OR build a report which displays the dependency and lag. Both items if possible.

Amanda Damstetter Answered

Please sign in to leave a comment.

3 comments

0
Avatar

Hi Amanda. This is possible to do with the Excel Addin, Dependency Lag is available as a field available if you select Links >> Dependencies. I don't know how to do it within the Clarizen App. However, you can add Predecessors into your view as a panel in a Work Plan View and customize the fields that show up in the panel. In the image below 5d is the lag. All you need to do is edit a Work Plan view and select Lag as a field for the panel. Then you can see the lag just by selecting any task.



Josh Santos 0 votes
Comment actions Permalink
0
Avatar

Thanks Josh.  This is how we already have our plans set up.  We are wanting to export and review the project with lag time defined in a column.  The current set up does not allow for broad review of the project and lags it requires you to click to each individual task to review the predecessor lag.  Ultimately, we are looking to save some time from a high-level view for our PM team.

Amanda Damstetter 0 votes