Post

3 followers Follow
0
Avatar

Resource load remaining effort in weekly view does not show work week

Using the Resource load view in Weeks, it shows the weekly period incorrectly (week does not start on a Monday). Not having working weeks in this view makes resource planning extremely difficult (except for the ongoing week)

CR-355558

Anat Segal Not planned

Please sign in to leave a comment.

1 comment

0
Avatar

For the 'Weekly' period option, I'd like the ability to have the Resource Load/Planning views to be able to default to showing the system set designated work week.

I.e. In our system our work week starts on M and ends on Su. I'd like the weekly view to start on M and end on Su by default. If someone chose to review a different 7-day view, they should then be able to adjust accordingly.

 

 

 

I see this one is set to 'Not Planned'. Should I create an additional request for this? Or will this get updated if more customers happened to request this feature.

James Bridgewater 0 votes
Comment actions Permalink