Ad hoc generation of "Tasks to be updated"

Hi,

  Every Monday, I receive "Time to update your progress" email, which contains the list of tasks to be updated for every project configured in Clarizen.

I have a need to generate the same email containing same information on an Ad hoc basis. How do I generate it manually ? 

I tried using Project Highlight Report for a project, but not only the email looks different, it also contains different information. 

I am ok with the current auto generated emails every monday, but I want to know to generate same email manually. 

Regards,

Nish

Nishant Kumar Answered

Please sign in to leave a comment.

2 comments

0
Avatar

In the work plan, you would select a work item then in the ribbon go to Common >> Email >> Send Update Request.

Josh Santos 0 votes
Comment actions Permalink
0
Avatar

Hi Josh,

   I tried doing that, I get a pop-up notification "Progress update Request was sent", but no emails were received. Tried a few work items, but no emails. 

Does it require some sort of configuration ?

 

Regards,

Nishant

Nishant Kumar 0 votes