Custom Action - Insert new Task into an existing Milestone

I'm trying to insert a new Task into an existing Milestone as shown below.  I tried to use $Project in the Parent field, but it was not inserted into the Milestone I selected.

If I use $Name in the Parent field I get an error message saying it can't find the existing Milestone that I'm trying to insert the Task into.  The Milestone name is 'Blue'

 

Brad Stern Answered

Please sign in to leave a comment.

2 comments

0
Avatar

Hello Brad,

You need to pass a reference to that milestone in the $Parent field. For example "M-123456" or a field that contains a milestone reference.

I hope this helps.

Roland

Roland Pumputis 0 votes
Comment actions Permalink
0
Avatar

Keep in mind there is no $Milestone field, it would have to be a specific reference to a milestone as Roland mentioned.

Josh Santos 0 votes