Same question but for Project
Post
FollowChange Task State with Custom Action
Hello,
How can I change the task state within a project plan using a custom action based on a criteria (criteria is known and works fine). I cannot seem to get the state to update on the task from completed to active. I have attached a screenshot with my current config. Please disregard any commented out code as it is not relevant and was used for test purposes only.
Please sign in to leave a comment.
8 comments
Date
Votes
Hello Cody and Devlend,
It should work if the evaluation criteria is TRUE. Demo: https://www.screencast.com/t/VZGl5alR
CA:
I hope this helps.
Roland
Hi Roland,
That actually did not work. we tested it the wya you said below and it did not work. Please advise on what we should try next.
thanks
Hello Cody,
What is your Leaf Tasks Progress Reporting Policy?
Thank you,
Roland
Roland - I am not entirely sure what you are asking if I am being honest.
Roland,
I work with Cody and the Leak Tasks Progress Reporting Policy was set to Individual. I changed it to Shared and ran the custom action. It did not change the completed tasks to active.
Hi Crisha,
Is it possible the $C_CompletedTasksturnActive is FALSE? Could you try moving the Change State action outside of Conditional Action List to see if this helps?
If it does not, please raise a support ticket and we'll take a closer look.
Thank you,
Roland
Thank you Roland for trying to answer this. I think we have found a work around for this. If we need any more help with this, we will open a support ticket.