Adding Dependencies

Adding Dependencies

This page describes creating dependencies between selected work items and includes the following sections:

About Dependencies

According to standard methodology, a dependency is a logical schedule link between two project work items, and defines the
sequence of work between them, for example, launch can be performed only after product is developed.
Clarizen d ependencies refer to which work items are predecessors−or ‘dependent’−upon others.

Adding a dependency between work items automatically changes the start or finish date of the successor work item.

Note: Dates that are manually set are not overridden when creating dependencies.

Dependency Types

Clarizen enables selecting from four schedule dependency types:

  • Finish to Start (FtS) — The successor work item begins upon completion of the predecessor work item
  • Finish to Finish (FtF) Predecessor work item does not finish until the successor is finished
  • Start to Finish (StF) The successor work item does not finish until the predecessor starts
  • Start to Start (StS) The successor work item does not start before the predecessor starts

Adding a Dependency

  1. Select a work item.

Figure 1: Selected Work Item

  1. On the ribbon, click and then click (or ).

    The Add Predecessors (or Add Successors ) dialog opens.

Figure 2: Add Predecessors

  1. Select and add a predecessor (or predecessors) to the Your Selections column.
  2. Click the Dependency field.

Figure 3: Dependency Field

  1. From the pick-list, select the dependency type .

Figure 4: Select Dependency Type

  1. Click to set the dependency.
  2. Click to add the predecessor(s).

    The data is sent to the server.

Adding Multiple Work Item Dependencies

Dependencies can be added to one or more work items.

The example below describes adding dependencies to multiple work items in a Work Plan:

  1. Select work items .

Figure 5: Selected Work Items

  1. On the ribbon, click and then click (or ).

    The Add Dependency dialog opens.

​Figure 2: Add Dependency

Within the dialog you can select which of the two work items will be the predecessor work item or which work item depends
on the other. You can then select the dependency type, and enter the lag if relevant.

 
  1. Select the required option.
  2. Click , and from the drop-down menu, select the dependency type .
  • (Optional) Add a lag between predecessor and successor work items

  • To restore all manually set dates within the selected work items, and thereby allow the automatic date changes based
    on the dependency type, check the Restore check box.
  1. Click

    The data is sent to the server.
 

 

Have more questions? Submit a request

Comments