Adding Dependencies

Adding Dependencies

This page describes creating dependencies between selected work items and includes the following sections:

About Dependencies

According to standard methodology, a dependency is a logical schedule link between two project work items, and defines the
sequence of work between them, for example, launch can be performed only after product is developed.
Clarizen d ependencies refer to which work items are predecessors−or ‘dependent’−upon others.

Adding a dependency between work items automatically changes the start or finish date of the successor work item.

Note: Dates that are manually set are not overridden when creating dependencies.

Dependency Types

Clarizen enables selecting from four schedule dependency types:

  • Finish to Start (FtS) — The successor work item begins upon completion of the predecessor work item
  • Finish to Finish (FtF) Predecessor work item does not finish until the successor is finished
  • Start to Finish (StF) The successor work item does not finish until the predecessor starts
  • Start to Start (StS) The successor work item does not start before the predecessor starts

Adding a Dependency

  1. Select a work item.

Figure 1: Selected Work Item

  1. On the ribbon, click Add Related and then click Predecessors (or Successors).

    The Add Predecessors (or Add Successors ) dialog opens.​

Figure 2: Add Predecessors

  1. Select and add a predecessor (or predecessors) to the Your Selections column.
  2. Click the Dependency field.

Figure 3: Dependency Field

  1. From the pick-list, select the dependency type .

Figure 4: Select Dependency Type

  1. Click OK to set the dependency.
  2. Click OK to add the predecessor(s).

    The data is sent to the server.

Adding Multiple Work Item Dependencies

Dependencies can be added to one or more work items.

The example below describes adding dependencies to multiple work items in a Work Plan:

  1. Select work items .

Figure 5: Selected Work Items

  1. On the ribbon, click Add Related and then click Predecessors (or Successors).

    The Add Dependency dialog opens.

​Figure 2: Add Dependency

Within the dialog you can select which of the two work items will be the predecessor work item or which work item depends
on the other. You can then select the dependency type, and enter the lag if relevant.

 
  1. Select the required option.
  2. Click Finish to Start (FtS), and from the drop-down menu, select the dependency type .
  • (Optional) Add a lag between predecessor and successor work items

​ 

  • To restore all manually set dates within the selected work items, and thereby allow the automatic date changes based
    on the dependency type, check the Restore check box.
  1. Click OK 
    The data is sent to the server.
 

 

Have more questions? Submit a request

Comments

  • Avatar
    Monicatwa

    It's terribly difficult to follow your "help" articles when 1/3 of it is not there!
    For example:
    Figure 1: Selected Work Item

    On the ribbon, click and then click (or ).

    1. There is not Figure 1 or any other Figures for this article.
    2. Click what? and then click what?

    Very frustrating!

  • Avatar
    Tom Do

    Hello Monica,

    Can you provide us with a screenshot with what you are referring to?

  • Avatar
    Monicatwa

    I've tried pasting a screen shot in this message, but it does not work. Is there another way?

  • Avatar
    Larry Bear

    Hi Monica, the images have been fixed. Seems like they were not appearing for non-logged in members.

  • Avatar
    Monicatwa

    Thanks Larry. I was logged in - but today I can see them.

  • Avatar
    Joy Weinbaum

    I am also not seeing the same images. I am logged in as well. I don't believe this page has been fixed...

    I am not able to paste a copy of the screen shot but I have the same issue as the poster from April.

  • Avatar
    Josh Santos

    I can see the images, can you try clearing browser cache, applying OS updates, and restarting the computer?